Endorsement 104 Special conditions concerning the construction of dams and water reservoirs

It is agreed and understood that otherwise subject to the terms, exclusions,
provisions and conditions contained in the Policy or endorsed thereon, the Insurers
shall not indemnify the Insured in respect of

– grouting of soft rock areas and/or other additional safety measures even if their
necessity arises only during construction,
– expenses incurred for dewatering even if the quantities of water originally
expected are exceeded substantially,
– loss or damage due to breakdown of the dewatering system if such breakdown
could have been avoided by sufficient stand-by facilities,
– expenses incurred for additional sealing or waterproofing and additional facilities
for the discharge of run-off and/or underground water,
– loss or damage due to subsidence if caused by insufficient compacting,
– cracks and leakage.